PG&E TOPOCK COMPRESSOR STATION

Safeguarding California Highways – Asbestos Soil Remediation at PG&E Topock Compressor Station

250+
Truckloads of asbestos-contaminated soil removed
0
Compliance Issues Post Project

PG&E’s Topock Compressor Station, located near Needles, California, sits at a critical juncture for both energy infrastructure and state transportation routes. When buried asbestos-containing materials were discovered in a large soil pit adjacent to a major highway, PG&E and Jacobs Engineering turned to Alliance Environmental Services to manage the complex remediation.

The project carried high stakes: contaminated soil removal next to active highway corridors, strict environmental compliance requirements, and the need to protect both workers and the traveling public.

Challenge

The Topock project presented multiple challenges:

  • Location Risks: The buried asbestos-containing material sat directly adjacent to a major California highway, requiring advanced safety controls and traffic coordination.
  • Volume of Material: Thousands of tons of contaminated soil had to be safely excavated, contained, and transported.
  • Environmental Compliance: Strict state and federal regulations demanded careful handling, air monitoring, and disposal.
  • Coordination: The project required seamless collaboration between Alliance Environmental Services, Jacobs Engineering, and PG&E.

Solution

Solution

Alliance Environmental Services implemented a step-by-step remediation plan:

  1. Site Preparation: Established exclusion zones, safety barriers, and negative air monitoring systems to ensure worker and public protection.
  2. Excavation: Used heavy equipment and skilled operators to carefully remove asbestos-contaminated soil from the buried pit.
  3. Containment & Transportation: All contaminated materials were securely wrapped, loaded into lined trucks, and hauled off-site to approved disposal facilities.
  4. Highway Safety Coordination: Work was scheduled and coordinated to minimize disruption along the adjacent highway, keeping traffic flowing and crews protected.
  5. Environmental Oversight: Continuous monitoring and reporting ensured compliance with state and federal asbestos regulations.

The project concluded successfully, with over 250 truckloads of asbestos-contaminated soil safely removed and disposed of.

From Founder

"Alliance Environmental Services delivered on every front. Their team worked seamlessly with Jacobs and PG&E to remediate one of our most complex highway-adjacent sites. Safety, compliance, and professionalism were top-notch throughout the project."

— Project Manager
Jaobs Engineering
What we learned together

The Topock project reinforced a key lesson: environmental remediation demands both technical expertise and strong partnerships. By collaborating closely with Jacobs and PG&E, Alliance Environmental Services demonstrated that even high-risk, highway-adjacent asbestos remediation can be completed safely, efficiently, and to the highest compliance standards.

This project stands as a flagship example of Alliance’s ability to handle large-scale hazardous waste cleanup projects across California and beyond.

More Stories

Different challenges. 

Same precision.